Shotton Concrete Structures
UPM-Kymmene (UK) Ltd

Value: £2,200,000
Site clearance, earthworks, landscaping and construction of a reinforced concrete structure to bulk store and facilitate the feeding of raw materials via a series of conveyors.
Elements of the structure were over 15m high and cast to tight tolerances to receive the conveyors. Part of the structure was constructed within a sheet piled coffer dam assisted by well point dewatering as the formation was 6m below ground water table and within a sand strata.
Total of 500 tonnes of rebar, 4500m3 of concrete and 15000m2 of shuttering installed in 26 weeks.
All work was undertaken on a live operational site and involved extensive third party liaison, management by CHC.