The Project

Construction of a steel frame extension to an existing portal frame waste transfer building.

Erection of an 88m long x 29m wide steel portal frame extension to the existing waste transfer building complete with RC floor slab, internal substation/LV building, baler pit and high level gantry connected to an external bridge/walkway.

Firewalls were required to two elevations and the steelwork was painted to provide 60 minute fire protection.

New land drainage and roof drainage was installed and connection made to the existing sewer within the highway. An attenuation tank was also installed beneath the RC floor slab to reduce the surface water drainage discharge to greenfield rates.

The existing perimeter of the site meant restrictive working conditions, therefore all works were undertaken from inside the building.